Dept. of Trans. PROGRESS Serial No. Contract No. 11-354-13-14 04-1E6604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 71% 04-SCL-101-R25.3/R25.3 Federal Project: 04-SM-101-R20.4/R20.4 NONE 04-SOL-780-6.7/6.7 Progress payment No. 05 Payment period ending: 12-20-11 AMERICAN CIVIL CONTRUCTORS WEST COAST INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 255,490.00 71,870.00 2.a. Extra Work 50,260.81 7,639.93 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 305,750.81 79,509.93 5. Mobilization 80,750.00 0.00 6. Total Work Completed 386,500.81 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 386,500.81 79,509.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 79,509.93