Dept. of Trans. PROGRESS Serial No. Contract No. 11-265-10-10 04-1E9604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 77% 04-SCL-17-6.6/13.9 Federal Project: 04-SCL-25-1.5/1.5 NONE 04-SCL-85-R15.0/R17.7 Progress payment No. 03 Payment period ending: 09-20-11 MYERS AND SONS CONSTRUCTION LP 2554 MILLCREEK DRIVE SACRAMENTO CA 95833 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 598,460.06 79,465.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 598,460.06 79,465.00 5. Mobilization 62,000.00 0.00 6. Total Work Completed 660,460.06 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 660,460.06 79,465.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 79,465.00