Dept. of Trans. PROGRESS Serial No. Contract No. 12-206-09-14 04-1E9704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 30% 04-SOL-12-R14.1/19.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-12 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 683,153.75 433,524.25 2.a. Extra Work 6,829.25 6,829.25 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 689,983.00 440,353.50 5. Mobilization 228,000.00 48,000.00 6. Total Work Completed 917,983.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 917,983.00 488,353.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 488,353.50