Dept. of Trans. FINAL Serial No. Contract No. 14-119-07-29 04-1G0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SCL-9-0.0/7.0 Federal Project: HSST-P009(17) Progress payment No. 06 Payment period ending: 03-12-14 STEVENS CREEK QUARRY INC 12100 STEVENS CANYON ROAD CUPERTINO CA 95014 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 568,357.00 0.00 2.a. Extra Work 52,958.04 22,322.84 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 621,315.04 22,322.84 5. Mobilization 13,000.00 0.00 6. Total Work Completed 634,315.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 634,315.04 22,322.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,322.84