Dept. of Trans. PROGRESS Serial No. Contract No. 12-234-16-33 04-1G5704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 55% 04-SON-101-25.0/ .0 Federal Project: 04-SON-101-28.0/ .0 NHQ1-120(7E) Progress payment No. 02 Payment period ending: 08-20-12 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 493,795.96 287,456.02 2.a. Extra Work 5,984.52 5,984.52 b. Adjustment Comp. 3. Materials on Hand 33,537.35 0.00 4. Earned Subject to Retention 533,317.83 293,440.54 5. Mobilization 78,000.00 3,900.00 6. Total Work Completed 577,780.48 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 611,317.83 297,340.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,340.54