Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 16-237-17-48 04-1G8504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SM-92-5.4/6.2 HSST-PG 000C(391) Progress payment No. 011 Payment period ending: 05-02-16 DREAMBUILDER CONSTRUCTION CORP 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 862,902.30 0.00 2. a. Extra Work 34,937.49 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 897,839.79 0.00 5. Mobilization 79,000.00 0.00 6. Total Work Completed 976,839.79 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 966,839.79 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00