Dept. of Trans. PROGRESS Serial No. Contract No. 18-352-13-41 04-1G8704 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 81% Location: Federal Project: 04-SCL-152-13.8/14.7 HSNH-P152(94) Progress payment No. 007 Payment period ending: 12-20-18 GRANITE ROCK COMPANY PO BOX 50001 WATSONVILLE CA 950775001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,858,726.56 148.00 2. a. Extra Work 74,170.01 0.00 b. Adustment Comp. 59,799.07 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,992,695.64 148.00 5. Mobilization 370,000.00 0.00 6. Total Work Completed 3,362,695.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,362,695.64 148.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 148.00