Dept. of Trans. PROGRESS Serial No. Contract No. 13-203-14-05 04-1G9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 31% 04-CC-4-27.5/R29.0 Federal Project: NONE Progress payment No. 12 Payment period ending: 07-20-13 BAY CITIES/MYERS JV P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,737,967.57 1,239,153.08 2.a. Extra Work 527,632.67 3,341.87 b. Adjustment Comp. 10,000.00 0.00 3. Materials on Hand 1,179,746.68 38,435.76 4. Earned Subject to Retention 13,455,346.92 1,280,930.71 5. Mobilization 4,948,423.72 0.00 6. Total Work Completed 17,224,023.96 7. Deductions -25,780.00 -1,020.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,377,990.64 1,279,910.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,279,910.71