Dept. of Trans. PROGRESS Serial No. Contract No. 13-291-13-50 04-1G9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 41% 04-CC-4-27.5/R29.0 Federal Project: NONE Progress payment No. 15 Payment period ending: 10-20-13 BAY CITIES/MYERS JV P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,904,010.56 811,515.24 2.a. Extra Work 653,571.72 56,360.41 b. Adjustment Comp. 85,246.07 -3,707.79 3. Materials on Hand 955,418.59 -127,506.57 4. Earned Subject to Retention 16,598,246.94 736,661.29 5. Mobilization 4,948,423.72 0.00 6. Total Work Completed 20,591,252.07 7. Deductions -17,140.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,529,530.66 736,661.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 736,661.29