Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 16-060-14-58 04-1G9404 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 100% Location: Federal Project: 04-CC-4-27.5/R29.0 NONE Progress payment No. 044 Payment period ending: 02-29-16 BAY CITIES/MYERS JV PO BOX 6227 CONCORD CA 94524-6227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,852,110.18 124,656.00 2. a. Extra Work 1,981,576.03 0.00 b. Adustment Comp. 193,512.03 0.00 3. Materials on Hand 491,859.55 0.00 4. Earned Subject to Retention 44,519,057.79 124,656.00 5. Mobilization 5,208,867.07 0.00 6. Total Work Completed 49,236,065.31 7. Deductions -54,278.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 49,673,646.86 124,656.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 124,656.00