Dept. of Trans. PROGRESS Serial No. Contract No. 15-202-13-45 04-1J5204 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 57% Location: Federal Project: 04-SM-84-R28.8/R29.3 NONE 04-ALA-84-R0.5/R0.5 Progress payment No. 003 Payment period ending: 07-20-15 GORDON N. BALL, INC. 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 409,782.00 194,933.00 2. a. Extra Work 1,454.66 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 411,236.66 194,933.00 5. Mobilization 75,000.00 3,750.00 6. Total Work Completed 486,236.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 486,236.66 198,683.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 198,683.00