Dept. of Trans. PROGRESS Serial No. Contract No. 19-142-13-29 04-1J5614 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 8% Location: Federal Project: 04-SM-101-0.0/6.6 NONE 04-SCL-101-50.6/52.6 Progress payment No. 003 Payment period ending: 05-20-19 KIEWIT INFRASTRUCTURE WEST CO. 4650 BUSINESS CENTER DR FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,913,940.89 5,050,849.81 2. a. Extra Work 137,146.42 120,903.52 b. Adustment Comp. 3. Materials on Hand 164,645.00 164,645.00 4. Earned Subject to Retention 10,215,732.31 5,336,398.33 5. Mobilization 4,462,500.00 1,487,500.00 6. Total Work Completed 14,513,587.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,678,232.31 6,823,898.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,823,898.33