Dept. of Trans. PROGRESS Serial No. Contract No. 20-056-09-37 04-1J5614 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 48% Location: Federal Project: 04-SM-101-0.0/6.6 NONE 04-SCL-101-50.6/52.6 Progress payment No. 012 Payment period ending: 02-20-20 KIEWIT INFRASTRUCTURE WEST CO. 4650 BUSINESS CENTER DR FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 50,627,370.04 2,975,613.22 2. a. Extra Work 3,196,966.81 65,297.54 b. Adustment Comp. -530,178.09 -81,363.27 3. Materials on Hand 0.00 -264,215.00 4. Earned Subject to Retention 53,294,158.76 2,695,332.49 5. Mobilization 5,950,000.00 0.00 6. Total Work Completed 59,244,158.76 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 59,244,158.76 2,695,332.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,695,332.49