Dept. of Trans. PROGRESS Serial No. Contract No. 16-355-14-08 04-1J5804 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 44% Location: Federal Project: 04-ALA-880-28.2/28.2 NONE Progress payment No. 003 Payment period ending: 12-20-16 CERTIFIED COATINGS CO. 2320 CORDELIA RD FAIRFIELD CA 94534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,041,249.06 325,281.63 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,041,249.06 325,281.63 5. Mobilization 313,500.00 0.00 6. Total Work Completed 1,354,749.06 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,354,749.06 325,281.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 325,281.63