Dept. of Trans. FINAL Serial No. Contract No. 21-313-14-50 04-1J6004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-0 HSNH-X001(510) Progress payment No. 015 Payment period ending: 06-17-21 DREAMBUILDER CONSTRUCTION CORP 18543 YORBA LINDA BLVD #376 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,411,326.26 135,906.54 2. a. Extra Work 237,078.56 121,980.68 b. Adustment Comp. -134,000.00 -134,000.00 3. Materials on Hand 4. Earned Subject to Retention 1,514,404.82 123,887.22 5. Mobilization 160,860.50 0.00 6. Total Work Completed 1,675,265.32 7. Deductions -2,200.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,673,065.32 123,887.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 123,887.22