Dept. of Trans. PROGRESS Serial No. Contract No. 16-354-15-17 04-1J6304 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 100% Location: Federal Project: 04-SCL-101-16.0/27.9 NHP-Q101(283) Progress payment No. 008 Payment period ending: 12-20-16 GRANITE CONSTRUCTION COMPANY 715 COMSTOCK ST SANTA CLARA CA 95054 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,365,647.25 52,262.76 2. a. Extra Work 9,449.37 0.00 b. Adustment Comp. 842,107.39 0.00 3. Materials on Hand 4. Earned Subject to Retention 13,217,204.01 52,262.76 5. Mobilization 1,365,000.00 0.00 6. Total Work Completed 14,582,204.01 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,582,204.01 52,262.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,262.76