Dept. of Trans. PROGRESS Serial No. Contract No. 16-322-15-31 04-1J6904 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 80% Location: Federal Project: 04-SF-101-1.6/4.1 NONE Progress payment No. 003 Payment period ending: 11-20-16 ARROW FENCING PO BOX 385 CALPELLA CA 95418 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 308,259.00 126,905.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 308,259.00 126,905.00 5. Mobilization 500.00 25.00 6. Total Work Completed 308,759.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 308,759.00 126,930.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 126,930.00