Dept. of Trans. PROGRESS Serial No. Contract No. 21-081-13-45 04-1J7004 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 82% Location: Federal Project: 04-ALA-123-2.8/2.8 SNHG-P123(4) Progress payment No. 009 Payment period ending: 03-20-21 CALIFORNIA HIGHWAY CONSTRUCTION GROUP INC 1647 WILLOW PASS RD #150 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 510,353.10 0.00 2. a. Extra Work 18,630.00 8,630.00 b. Adustment Comp. -586.87 0.00 3. Materials on Hand 4. Earned Subject to Retention 528,396.23 8,630.00 5. Mobilization 75,500.00 0.00 6. Total Work Completed 603,896.23 7. Deductions -3,680.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 600,216.23 8,630.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,630.00