Dept. of Trans. PROGRESS Serial No. Contract No. 16-020-16-23 04-1J7604 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 80% Location: Federal Project: 04-SOL-80-39.8/39.8 NONE Progress payment No. 004 Payment period ending: 01-20-16 CE GREEN INC 6105 MAIN AVENUE, SUITE 4 ORANGEVALE CA 95662 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 346,972.50 71,345.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 346,972.50 71,345.00 5. Mobilization 6. Total Work Completed 346,972.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 346,972.50 71,345.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,345.00