Dept. of Trans. PROGRESS Serial No. Contract No. 15-051-10-33 04-1J8004 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 100% Location: Federal Project: 04-ALA-13-0.1 NONE Progress payment No. 007 Payment period ending: 02-20-15 BAUMAN LANDSCAPE & CONSTRUCTION, INC 1255 BATTERY STREET, STE 400 SAN FRANCISCO, CA 94111 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 989,883.33 52,050.04 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 989,883.33 52,050.04 5. Mobilization 6. Total Work Completed 989,883.33 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 989,883.33 52,050.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,050.04