Dept. of Trans. PROGRESS Serial No. Contract No. 18-022-14-15 04-1J8204 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 88% Location: Federal Project: 04-SOL-80-17.1/17.1 NONE Progress payment No. 004 Payment period ending: 01-20-18 GD LONG ELECTRIC COMPANY 450 TECHNOLOGY WAY NAPA CA 94558 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 425,932.52 82,412.52 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 425,932.52 82,412.52 5. Mobilization 6. Total Work Completed 425,932.52 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 405,932.52 72,412.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 72,412.52