Dept. of Trans. FINAL Serial No. Contract No. 18-309-13-38 04-1J8204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SOL-80-17.1/17.1 NONE Progress payment No. 010 Payment period ending: 05-11-18 GD LONG ELECTRIC COMPANY 450 TECHNOLOGY WAY NAPA CA 94558 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 804,443.05 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 804,443.05 0.00 5. Mobilization 6. Total Work Completed 804,443.05 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 804,443.05 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00