Dept. of Trans. PROGRESS Serial No. Contract No. 25-050-17-30 04-1J9604 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 22% Location: Federal Project: 04-MRN-1-22.8/33.0 ACST-P001(693) 04-MRN-1-45.0/50.5 Progress payment No. 009 Payment period ending: 02-20-25 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,222,418.91 -292,000.00 2. a. Extra Work 417,631.71 97,699.42 b. Adustment Comp. 3. Materials on Hand 165,165.00 0.00 4. Earned Subject to Retention 3,805,215.62 -194,300.58 5. Mobilization 980,400.00 0.00 6. Total Work Completed 4,620,450.62 7. Deductions 0.00 199,186.62 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,785,615.62 4,886.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,886.04