Dept. of Trans. PROGRESS Serial No. Contract No. 23-052-13-16 04-1J9704 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 44% Location: Federal Project: 04-SCL-17-2.8/13.9 ACNH-P017(117) Progress payment No. 019 Payment period ending: 02-20-23 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,873,387.94 405,725.66 2. a. Extra Work 1,930,750.41 614,534.93 b. Adustment Comp. 1,167,483.65 0.00 3. Materials on Hand 4. Earned Subject to Retention 28,971,622.00 1,020,260.59 5. Mobilization 1,750,000.00 0.00 6. Total Work Completed 30,721,622.00 7. Deductions -36,750.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,684,872.00 1,020,260.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,020,260.59