Dept. of Trans. FINAL Serial No. Contract No. 22-131-16-06 04-1J9904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-13-5.2/5.5 ACHS-NH00-0(C50) 04-CC-24-1.0/R2.5 04-CC-24-R4.2/R5.0 Progress payment No. 020 Payment period ending: 06-28-21 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,357,568.20 0.00 2. a. Extra Work 471,532.97 1,591.15 b. Adustment Comp. 123,822.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,952,923.17 1,591.15 5. Mobilization 459,000.00 0.00 6. Total Work Completed 5,411,923.17 7. Deductions -6,701.00 -6,701.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,405,222.17 -5,109.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -5,109.85