Dept. of Trans. PROGRESS Serial No. Contract No. 17-128-11-08 04-1K4804 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 80% Location: Federal Project: 04-ALA-13-0.0 NONE Progress payment No. 007 Payment period ending: 03-16-17 BAY AREA TREE SPECIALIST 541 W. CAPITOL EXPWY #287 SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 403,126.51 44,234.96 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 403,126.51 44,234.96 5. Mobilization 6. Total Work Completed 403,126.51 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 403,126.51 44,234.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,234.96