Dept. of Trans. PROGRESS Serial No. Contract No. 17-055-16-25 04-1K6504 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 98% Location: Federal Project: 04-SM-1-36.2/36.2 NONE Progress payment No. 007 Payment period ending: 01-20-17 GRANITE ROCK COMPANY 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 842,986.71 68,628.91 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 842,986.71 68,628.91 5. Mobilization 6. Total Work Completed 842,986.71 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 842,986.71 68,628.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,628.91