Dept. of Trans. PROGRESS Serial No. Contract No. 16-348-15-26 04-1K8404 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 46% Location: Federal Project: 04-SF-1-0.0 NONE Progress payment No. 004 Payment period ending: 11-30-16 KINGSBOROUGH ATLAS TREE SURGERY INC 1544 LUDWIG AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 781,767.93 214,091.33 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 781,767.93 214,091.33 5. Mobilization 6. Total Work Completed 781,767.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 781,767.93 214,091.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 214,091.33