Dept. of Trans. PROGRESS Serial No. Contract No. 18-233-08-54 04-1Q3704 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 24% Location: Federal Project: 04-SCL-17-0.0/1.0 NONE Progress payment No. 001 Payment period ending: 08-20-18 RGW CONSTRUCTION INC 6267 SOUTHFRONT RD LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 494,106.19 494,106.19 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 494,106.19 494,106.19 5. Mobilization 6. Total Work Completed 494,106.19 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 484,106.19 484,106.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 484,106.19