Dept. of Trans. PROGRESS Serial No. Contract No. 25-324-10-12 04-1Q4604 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 95% Location: Federal Project: 04-SCL-280-R0.0/R2.7 ACIM-2801(992) Progress payment No. 009 Payment period ending: 11-20-25 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,106,127.02 540,925.55 2. a. Extra Work 38,955.78 38,955.78 b. Adustment Comp. 3. Materials on Hand 147,688.00 0.00 4. Earned Subject to Retention 14,292,770.80 579,881.33 5. Mobilization 1,865,000.00 0.00 6. Total Work Completed 16,010,082.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,157,770.80 579,881.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 579,881.33