Dept. of Trans. PROGRESS Serial No. Contract No. 24-165-11-52 04-1Q5204 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 04-SCL-880-1.7/1.8 NONE Progress payment No. 006 Payment period ending: 06-20-24 DISNEY CONSTRUCTION INC 533 AIRPORT BLVD #120 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,365,738.00 121,690.00 2. a. Extra Work 29,241.27 29,241.27 b. Adustment Comp. -12,929.77 -12,929.77 3. Materials on Hand 4. Earned Subject to Retention 1,382,049.50 138,001.50 5. Mobilization 140,000.00 0.00 6. Total Work Completed 1,522,049.50 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,512,049.50 128,001.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 128,001.50