Dept. of Trans. PROGRESS Serial No. Contract No. 26-140-14-45 04-1Q8204 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 19% Location: Federal Project: 04-SF-101-0.0/4.9 ACNH-Q101(454) Progress payment No. 008 Payment period ending: 05-20-26 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,798,617.37 2,076,096.20 2. a. Extra Work 471,880.33 329,014.98 b. Adustment Comp. 3. Materials on Hand 1,195,005.06 0.00 4. Earned Subject to Retention 15,465,502.76 2,405,111.18 5. Mobilization 6,916,650.00 0.00 6. Total Work Completed 21,187,147.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,382,152.76 2,405,111.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,405,111.18