Dept. of Trans. PROGRESS Serial No. Contract No. 22-047-10-23 04-1Q8704 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 04-SON-128-24.2/24.7 NONE 04-NAP-128-0.0/1.1 04-NAP-128-18.7/22.2 Progress payment No. 030 Payment period ending: 02-20-22 BORTOLUSSI AND WATKIN INC 77 LARKSPUR ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 424,057.45 5,341.25 2. a. Extra Work 31,223.21 18,669.37 b. Adustment Comp. -44,733.04 -2,670.63 3. Materials on Hand 4. Earned Subject to Retention 410,547.62 21,339.99 5. Mobilization 64,900.00 0.00 6. Total Work Completed 475,447.62 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 465,447.62 21,339.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,339.99