Dept. of Trans. PROGRESS Serial No. Contract No. 06-139-08-42 04-1S2814 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 19% 04-SON-116-4.4/21.3 Federal Project: ER-35M0(4) Progress payment No. 03 Payment period ending: 05-20-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 295,010.57 268,433.07 2.a. Extra Work 6,915.74 0.00 b. Adjustment Comp. 3. Materials on Hand 67,378.69 67,378.69 4. Earned Subject to Retention 369,305.00 335,811.76 5. Mobilization 141,550.00 141,550.00 6. Total Work Completed 443,476.31 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 510,855.00 477,361.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 477,361.76