Dept. of Trans. PROGRESS Serial No. Contract No. 06-354-07-56 04-1S9614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 93% 04-MRN-1-25.5/25.7 Federal Project: ER-35L8(4) Progress payment No. 03 Payment period ending: 12-20-06 MAGGIORA AND GHILOTTI INC 555 DUBOIS ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 195,931.10 1,701.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 45,017.52 45,017.52 4. Earned Subject to Retention 240,948.62 46,718.52 5. Mobilization 6. Total Work Completed 195,931.10 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -4,671.85 -4,671.85 c. Reduction after 95% Comp. 9. Total pay to Contractor 236,276.77 42,046.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,046.67