Dept. of Trans. PROGRESS Serial No. Contract No. 12-117-15-25 04-1SS274 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 100% 04-SM-280-6.7 Federal Project: NONE Progress payment No. 05 Payment period ending: 04-26-12 HALF MOON BAY GRADING & PAVING 1780 HIGGINS CANYON ROAD HALF MOON BAY, CA 94019 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,000.00 0.00 2.a. Extra Work 639,916.81 115,727.76 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 658,916.81 115,727.76 5. Mobilization 6. Total Work Completed 658,916.81 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 658,916.81 115,727.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,727.76