Dept. of Trans. PROGRESS Serial No. Contract No. 16-140-13-31 04-1SS474 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 38% Location: Federal Project: 04-CC-680-10.4 NHPI-680 1-067(E) Progress payment No. 002 Payment period ending: 05-20-16 RGW CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 887,582.00 653,157.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 887,582.00 653,157.00 5. Mobilization 242,250.00 51,000.00 6. Total Work Completed 1,129,832.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,129,832.00 704,157.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 704,157.00