Dept. of Trans. PROGRESS Serial No. Contract No. 17-205-12-49 04-1SS584 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 62% Location: Federal Project: 04-MRN-1-2.2 ACNH-P001(619) Progress payment No. 001 Payment period ending: 07-20-17 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 95,360.00 95,360.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 81,743.53 81,743.53 4. Earned Subject to Retention 177,103.53 177,103.53 5. Mobilization 93,750.00 93,750.00 6. Total Work Completed 189,110.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 270,853.53 270,853.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 270,853.53