Dept. of Trans. PROGRESS Serial No. Contract No. 17-233-14-19 04-1SS584 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 35% Location: Federal Project: 04-MRN-1-2.2 ACNH-P001(619) Progress payment No. 002 Payment period ending: 08-20-17 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 862,850.00 767,490.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -81,743.53 4. Earned Subject to Retention 862,850.00 685,746.47 5. Mobilization 125,000.00 31,250.00 6. Total Work Completed 987,850.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 987,850.00 716,996.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 716,996.47