Dept. of Trans. PROGRESS Serial No. Contract No. 16-355-11-34 04-1SS594 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 89% Location: Federal Project: 04-MRN-580-2.7/2.7 NONE Progress payment No. 003 Payment period ending: 12-20-16 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 371,560.25 10,096.00 2. a. Extra Work 9,201.86 9,201.86 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 380,762.11 19,297.86 5. Mobilization 6. Total Work Completed 380,762.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 380,762.11 19,297.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,297.86