Dept. of Trans. PROGRESS Serial No. Contract No. 24-171-10-20 04-1W0604 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 100% Location: Federal Project: 04-SF-80-7.7/7.7 NONE Progress payment No. 034 Payment period ending: 06-19-24 CALIFORNIA ENGINEERING CONTRACTORS,INC 20 HAPPY VALLEY RD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 10,185,989.61 64,314.80 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,185,989.61 64,314.80 5. Mobilization 6. Total Work Completed 10,185,989.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,185,989.61 64,314.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 64,314.80