Dept. of Trans. FINAL Serial No. Contract No. 21-092-08-20 04-1W4204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-880-29.7/29.7 NONE Progress payment No. 002 Payment period ending: 02-11-21 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,280.00 0.00 2. a. Extra Work 27,105.48 589.18 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 28,385.48 589.18 5. Mobilization 6. Total Work Completed 28,385.48 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,385.48 589.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 589.18