Dept. of Trans. FINAL Serial No. Contract No. 22-224-10-14 04-1W9804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SF-101-4.3/L4.3 NONE Progress payment No. 006 Payment period ending: 09-30-21 YERBA BUENA ENGINEERING AND CONSTRUCTION INC 1340 EGBERT AVENUE SAN FRANCISCO CA 94124 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,789.24 0.00 2. a. Extra Work 562,428.04 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 566,217.28 0.00 5. Mobilization 6. Total Work Completed 566,217.28 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 566,217.28 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00