Dept. of Trans. PROGRESS Serial No. Contract No. 25-167-08-18 04-1X3604 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 76% Location: Federal Project: 04-SOL-28-0.0/R9.8 NONE Progress payment No. 004 Payment period ending: 06-20-25 REDGWICK CONSTRUCTION CO. 21 HEGENBERGER CT OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 252,242.31 113,432.92 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 252,242.31 113,432.92 5. Mobilization 6. Total Work Completed 252,242.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -11,343.29 -11,343.29 c. Reduction after 95% Comp. 9. Total pay to Contractor 240,899.02 102,089.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 102,089.63