Dept. of Trans. PROGRESS Serial No. Contract No. 25-212-09-27 04-1X3604 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 19% Location: Federal Project: 04-SOL-28-0.0/R9.8 NONE Progress payment No. 006 Payment period ending: 07-31-25 REDGWICK CONSTRUCTION CO. 21 HEGENBERGER CT OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 545,158.93 108,420.46 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 545,158.93 108,420.46 5. Mobilization 6. Total Work Completed 545,158.93 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 545,158.93 108,420.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,420.46