Dept. of Trans. PROGRESS Serial No. Contract No. 25-107-08-52 04-1X3804 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 17% Location: Federal Project: 04-ALA-880-0.0/R28.9 NONE Progress payment No. 002 Payment period ending: 04-16-25 ANVIL BUILDERS INC 1550 PARK AVE EMERYVILLE CA 94608 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 199,952.92 145,353.52 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 199,952.92 145,353.52 5. Mobilization 6. Total Work Completed 199,952.92 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 199,952.92 145,353.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,353.52