Dept. of Trans. PROGRESS Serial No. Contract No. 25-178-10-56 04-1X3804 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 23% Location: Federal Project: 04-ALA-880-0.0/R28.9 NONE Progress payment No. 004 Payment period ending: 05-30-25 ANVIL BUILDERS INC 1550 PARK AVE EMERYVILLE CA 94608 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 729,095.15 100,289.15 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 729,095.15 100,289.15 5. Mobilization 6. Total Work Completed 729,095.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 729,095.15 100,289.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,289.15