Dept. of Trans. PROGRESS Serial No. Contract No. 25-142-10-06 04-1X9604 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 38% Location: Federal Project: 04-SM-82-9.2/9.2 NONE Progress payment No. 002 Payment period ending: 05-22-25 SANTAMARIA CONCRETE INC PO BOX 8468 SAN JOSE CA 95155-8468 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 99,514.75 10,633.76 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 99,514.75 10,633.76 5. Mobilization 6. Total Work Completed 99,514.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 99,514.75 10,633.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,633.76