Dept. of Trans. PROGRESS Serial No. Contract No. 23-298-11-11 04-1Y0904 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 60% Location: Federal Project: 04-ALA-24-R5.9 NONE Progress payment No. 001 Payment period ending: 10-20-23 BROSAMER & WALL INC 1777 OAKLAND BLVD #110 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 416,675.00 416,675.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 416,675.00 416,675.00 5. Mobilization 75,000.00 75,000.00 6. Total Work Completed 491,675.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 491,675.00 491,675.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 491,675.00