Dept. of Trans. PROGRESS Serial No. Contract No. 05-293-10-09 04-203804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 82% 04-SM-101-23.7/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-05 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY RD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 353,851.20 351,351.20 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 353,851.20 351,351.20 5. Mobilization 38,000.00 38,000.00 6. Total Work Completed 391,851.20 7. Deductions 8. a.Contract Retentions -17,692.56 -17,442.56 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 374,158.64 371,908.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 371,908.64